Energy Concepts - References
Old/New Port Bremerhaven

|
An energy solution needed to be developed for the free space around the Old and New port in Bremerhaven. Based on the expected use and the planned construction activities, we developed energy supply models and conducted a cost-benefit analysis. We analyzed and compared the installation of a decentralized (natural gas) supply system with centralized district heating, combined heat and power, and biomass solutions. Furthermore, we provided ideas on energy efficient planning and innovative supply for the constructions to be planned. |
|
| Customer | Bremerhavener Entwicklungsgesellschaft Alter/Neuer Hafen BEAN |
| Location | Bremerhaven |
| Technical Characteristics | |
| Heated area | 135,000 m² |
| Heating | 6,600 kW 9,500 MWh/a |
| Cooling | 4,400 kW 3,300 MWh/a |
| Power | 5,200 kW 10,800 MWh |
| Completion | January 2002 |